00The project involves the
construction of 17 clusters of injection wells, several groundwater observation
wells, and approximately 7,000 feet of parallel pipelines including 18-
to 30-inch steel water pipelines, 4- to 6-inch steel air pipelines, 2-inch
electrical and telemetry conduits, and a 10-inch gravity disposal pipeline.
The pipelines (and conduits) provide water to the injection wells, air
for back flushing the wells, a disposal line for removing wastewater from
the back flushing, electric power, and controls. Access manholes will
be constructed at each injection well cluster. The injection wells are
currently being constructed under a separate contract.
|