00The project involves the construction of 17 clusters of injection wells, several groundwater observation wells, and approximately 7,000 feet of parallel pipelines including 18- to 30-inch steel water pipelines, 4- to 6-inch steel air pipelines, 2-inch electrical and telemetry conduits, and a 10-inch gravity disposal pipeline. The pipelines (and conduits) provide water to the injection wells, air for back flushing the wells, a disposal line for removing wastewater from the back flushing, electric power, and controls. Access manholes will be constructed at each injection well cluster. The injection wells are currently being constructed under a separate contract.

Page 2 of 4